Hardisty Connectivity Project.

Completed detailed engineering and DBM for a pipeline connection to a terminal manifold. The scope involved:

  • NPS 36 pipeline (EP to YP) connectivity from terminal fenceline / right-of-way to manifold including receiving trap

  • Routing above grade on pipe racks and then underground until connection to the manifold

    • Connectivity at manifold included connections to the existing tank suction lines and the future tank to allow for crude deliveries from the new incoming pipeline to any of these tanks

  • Batch Detection Building

Pipeline Connection to Line Pump Suction scope involved:

  • NPS 36 pipeline to be connected to pump station suction - line was installed on new pipe rack that went south past the manifold

Pipeline Line 67 Connection to Line 4 scope involved:

  • Line 67 NPS 30 jump-over connection to Line 4 for emergency supply to Line 4 mainline pump

  • Emergency power to Emergency Shutdown Valves

Services Provided

  • Engineering

CLIENT SCHEDULE INDUSTRY

Enbridge 2012-2018 Energy